M6 Set up geophysical and geochemical acquisition (all regions)
M12 Overview of the European and national policy context for CCUS

2022

M14 Active 3D seismic survey in Paris Basin (FR) and gravity survey in Ebro Basin (ES)
M18 Community Acceptance: Findings from community profiles and first local survey
M18 The choice between the 2 possible sites: Onshore or Offshore in Lusitania Basin (PT) and Ebro Basin (ES). Aspects are technical and societal
M24 West Macedonia (GR) 2D seismic re-processing
M24 Citizen engagement strategy

2023

M35 Options of CCUS scenarios and concepts for the pilot plant and well design alternatives
M36 Injection strategy and storage capacity

2024

M45 Final CCUS concept proposed.
M45 Design of the 2nd survey on community public acceptance
M48 Computing and validation of the experimental design of Risk Assessment

2025

M56 Storage potential in Upper Silesia (PL) and West Macedonia (GR), including geochemical and geomechanical analysis
M58 Permit Dossier ready to take FID decision and legal requirements for the storage plant
M59 Pre-FEED study and Final proposal of CCUS concept